기후에 의한 대구지역 작업불능일 산정과 공동주택 공사의 일정관리
Estimate of non-working day and schedule of apartmant construction by weather factors in Daegu

  • 간행물
    대한건축학회지회연합회 학술발표대회논문집 바로가기
  • 권호(발행년)
    2010년도 추계학술발표대회 (2010.12) 바로가기
  • 페이지
    pp.422-425
  • 저자
    김덕진, 김정현, 안성훈
  • 언어
    한국어(KOR)
  • URL
    https://www.earticle.net/Article/A133820

원문정보

초록

영어
A current construction site is lacking of the step that applys introduction of non-working day to progress schedule by a weather element. Unlike construction schedule, if the weather has changed, it would have an effect on whole construction schedule because the air has been pushed.
Therefore, this study is pursued for help to supervision of construction schedule by taking an average of non-working day which depends on weather factors that based on data of weather Bureau for last 22years, through including holiday which is applied at real construction site and suggesting non-working day, and in this way that tie applying to construction schedule of apartments in with judging the optimum time of construction that is able to introduce statistically, at the same time.

목차

Abstract
 1. 서론
  1.1 연구의 배경 및 목적
  1.2 연구의 방법 및 범위
 2. 이론적 고찰
  2-1. 기후에 따른 작업 불능일 조건
  2-2. 휴일에 따른 작업불능일
 3. 기후에 따른 작업불능일 산정 결과
  3.1 평균 일강우량
  3.2 일일평균기온 0℃이하인 경우
  3.3 일일평균기온 25℃이상인 경우
  3.4 일일 기후에 따른 작업불능일
 4. 1 대구지역 작업 불능일 산정 결과 적용
 5. 결론
 참고문헌

저자

  • 김덕진 [ Kim, Duck-Jin | 대구대학교 건축공학과 학사과정 ]
  • 김정현 [ Kim, Jung-Hyun | 대구대학교 건축공학과 학사과정 ]
  • 안성훈 [ An, Sung-Hun | 대구대학교 건축공학과 조교수, 공학박사 ]